Phasing Plan Surf Rm, Grill Rm. & Docks and more, 5 years and beyond.                         

 

Phase 1- Surf room addition including handicapped bath, storage and coat room plus finish off the disturbed area above bar plus column enclosures and “soffit” separating the “porch”. At the same time complete the acoustical elements and new lighting—including the grill room coffered ceiling and the tray ceiling in the “porch” area.

 

Phase 2.Complete the Grill Room bathrooms, new trophy case and alcove upgrade, as well as installing the East window wall- new energy efficient windows facing the water.  At this point we should begin obtaining engineering  and permits we can begin driving piles for the new floats in year 3

 

Phase 3. Install all required pilings for the new floating dock system and 1 new float at launch in order to keep the launch operating without having a conflict with the new pilings

 

Phase 4. Install North-South floats.

 

Phase 5. Install East-West floats.

 

Phase 6 and beyond. Relocate the grill room bar as envisioned in the Morrison Plan if it is approved by the membership .Investigate the possibility of adding decks over the roofs of the lower yard buildings to replace the lost deck space if the bar is moved. Extensively re-grade the North lot, pave and fence off  to create 16 to 18 new parking spaces

 

The above “phases” can be considered a “priority” list rather than a list of projects by the year as actually completing and funding each project in this time frame is unlikely and dependant upon the approval of capital funding  by the membership to approve the funding at this rate.

We, the Planning Committee, believe we should move forward with this well conceived Master Plan while we investigate the possibilities and funding of the relocation of the bar. There is nothing in the Master Plan that will prohibit the bar relocation if the membership desires this project.

 

Respectfully Submitted,

Planning Committee 2006


Back